To-Do:
* Build a test device and check if everything is okay
* Create the keymat mould (takes 20 - 25 days)
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!
I love the way "mass production" is just a single bullet point...

It's a bit like that scene in Red Dwarf (the UK sci-fi sitcom) where they capture Hitler's diary and it's full of stuff like "To Do Today: Buy some milk, feed the cat, annex Czechoslovakia."

Incidentally, is their claim to be "by far the most powerful handheld in the world both in terms of raw CPU power and 3D graphics" valid any more, even if they shipped tomorrow? Or are they only comparing themselves to handheld games consoles?