As they say, make an estimate. Try to make it a realistic estimate. Double the time. THEN you have a realistic estimate. Double that. THEN you have the actual time needed.
|
2009-05-04
, 22:39
|
|
Posts: 3,096 |
Thanked: 1,525 times |
Joined on Jan 2006
@ Michigan, USA
|
#134
|
|
2009-05-04
, 23:16
|
|
Posts: 1,310 |
Thanked: 820 times |
Joined on Mar 2006
@ Irving, TX
|
#135
|
|
2009-05-04
, 23:34
|
|
Posts: 4,783 |
Thanked: 1,253 times |
Joined on Aug 2007
@ norway
|
#136
|
|
2009-05-04
, 23:37
|
|
Posts: 3,096 |
Thanked: 1,525 times |
Joined on Jan 2006
@ Michigan, USA
|
#137
|
could be that someone is forgetting to edit it, who knows.
not that i care much any longer. it will ship when it ships, or not at all.
|
2009-05-04
, 23:57
|
|
Posts: 4,783 |
Thanked: 1,253 times |
Joined on Aug 2007
@ norway
|
#138
|
|
2009-05-05
, 19:56
|
|
Posts: 1,540 |
Thanked: 1,045 times |
Joined on Feb 2007
|
#139
|
To-Do:
* Build a test device and check if everything is okay
* Create the keymat mould (takes 20 - 25 days)
* Create mould of final case (can be done once the case fits, takes 30 - 35 days)
* CE / FCC testing (can be done once the prototype case is here)
* Mass Production testrun for the final boards
* Stability testing (this will be fun)
* Wait for the last remaining pieces for mass production (LATEST deadline is second week of March)
* Mass Production
* Test the boards
* SHIP THEM!
|
2009-05-05
, 20:18
|
|
Posts: 5,478 |
Thanked: 5,222 times |
Joined on Jan 2006
@ St. Petersburg, FL
|
#140
|
Incidentally, is their claim to be "by far the most powerful handheld in the world both in terms of raw CPU power and 3D graphics" valid any more, even if they shipped tomorrow?
|
3-time Maemo Community Council Member
Co-Founder, Hildon Foundation